We had some bad luck with the weather and concrete got canceled on us two weeks in a row, so we had to mix 7 yards of concrete with this machine, i almost had a mutiny, but we got it done about $500 over budget we couldn't wait any longer. if we had waited another weekend it would have pushed us back 2 weeks.

The pictures above and below are the same view of the front of the house.


This is looking out the back of the house, there will be a car port outside this window.

This is another view of the front completely framed out. (looking good) We will be finishing the roof, siding electric, hardwood, windows and carport all this week. by Monday June 30th it should look like a real house. We are however having a little issue with the HVAC, no one wants to do it for what i want to pay, ill keep you posted. Right now i am over budget about $2000.00 and have quite a bit to go so i have to watch my pennies.